|
TRIDENT II D5 BACKFITS
By HOWARD G. KRAMER
Puget Sound Naval Shipyard modernizes the sea-based
U.S. deterrent force.
Howard G. Kramer is the D-5 missile project business
officer at Puget Sound Naval Shipyard.
On the warm and clear Saturday of 16 March 2002, official guests and
other observers of the Ohio-class fleet ballistic missile submarine (SSBN)
USS Alaska gathered aboard the surveying ship USNS Waters off the coast
of Florida to witness an important Navy Demonstration and Shakedown Operation
(DASO). At approximately 4:00 p.m. the assembled group had the privilege
of witnessing the successful launching from the Alaska of a Trident II
D5 missile. The launch was important because Alaska is the first Ohio-class
Trident SSBN to be retrofitted to the Trident II D5 configuration from
its earlier Trident I C4 missile configuration. The successful execution
of the DASO, carried out by members of the Alaska Gold crew, marked not
only the beginning of the end of the Trident I C4 missile era, but also
the successful completion of the first of four Ohio-class Trident D5 backfits
being accomplished by the Puget Sound Naval Shipyard (PSNSY) in Bremerton,
Wash. The successful DASO also reflected the countless hours spent by
both public and private-sector activities, and by Alaska Blue and Gold
crewmembers, who participated in the design, planning, execution, and
testing associated with the D5 backfit program.
Original Design Package Foresaw Need for Upgrading
The original design requirements of the Ohio-class SSBN took into account
the need to support future upgrading for the Trident II D5 missiles and
support systems. The first eight Trident SSBNs were outfitted with the
Trident I C4 missile and support systems, but the Navy's intention from
the start was to backfit all of these submarines with newer Trident II
D5 missiles and support systems--when they became available.
In September 1997, the Navy tasked Puget Sound Naval Shipyard to begin
developing a strategy for executing the Trident II D5 backfits as part
of the Alaska Engineered Overhaul (EOH). The Navy also tasked the Electric
Boat Division of General Dynamics to complete the Trident II D5 backfit
design package that had been in various stages of development since the
mid-1980s. The taskings included an additional requirement--to use commercial-off-the-shelf
(COTS) items in the design package where possible. Using COTS equipment
led to a major reduction in costs and ensured that the most updated technology
would be used during the backfits.
The herculean design effort that followed provided PSNSY with over 1,000
design products needed to support the D5 backfit installation and included
revisions to several thousand drawings. Electric Boat also was tasked
to procure, package per work-unit sequences, and ship to Puget Sound thousands
of line items of government furnished material/equipment for each D5 backfit.
The line items were shipped from numerous points throughout the continental
United States. Puget Sound's Engineering and Planning Department, Electric
Boat, the Naval Sea Systems Command (NAVSEA), the Navy's Strategic Systems
Program (SSP) office, and numerous SSP support contractors collaborated
to develop a "just-in-time" delivery schedule for the design
products and materials. The initial delivery schedule fully supported
the planning and execution schedules being developed by PSNSY.
One Team, One Plan
In January 1999, the project manager appointed for the Alaska EOH began
to assemble his project management team to plan and execute the 19-month
availability, which was scheduled to start on 1 May 2000. It would be
the first major submarine availability started at Puget Sound since the
USS Ohio EOH in fiscal year 1993. The Alaska EOH was to be the first of
four Trident II D5 backfits scheduled to be conducted by the Navy's only
West Coast shipyard. The Alaska project management team consisted of personnel
from PSNSY, the Alaska's ship's force, Submarine Squadron Seventeen, and
Naval Intermediate Maintenance Facility Pacific Northwest Bangor (NAVIMF
PACNORWEST).
One of the first decisions made by PSNSY was to invoke, as much as practical,
the NAVSEA Baseline Project Management Plan (BPMP) that was then under
development (and subsequently issued, in July 1999). The BPMP was introduced
to improve SSN 688 Los Angeles-class submarine performance, but the disciplined
planning processes reflected in the plan were applicable to the backfit
project as well.
One of the major challenges facing the project management team was that
of work force integration. A total of 17 organizations (eight private,
and nine public-sector) participated in the planning, execution, and testing
phases of the availability. To further increase the challenge, these 17
organizations received funding from three separate activities, each with
different budgeting priorities. The Trident II D5 backfit accounted for
approximately 55 percent of the workload; the remaining 45 percent included
periodic maintenance (by the ship's force), intermediate and depot-level
maintenance, and the installation of numerous modernization alterations,
not all of which were conjunctive to the Trident II D5 backfit.
The ship's force continued to perform routine periodic maintenance, and
NAVIMF PACNORWEST continued to plan and carry out most of the intermediate-level
maintenance. PSNSY planned and executed all of the Trident II D5 backfit,
most of the modernization alterations, and depot-level maintenance, as
well as those parts of the intermediate-level maintenance program that
would be affected by the D5 backfit.
Prior to the start of the availability Alaska Blue and Gold crews were
combined into a single crew. A combined crew was needed to accomplish
mandatory training and recertification requirements, accomplish ship's
force periodic maintenance, and provide the enormous amount of support
required by the project management team during the execution and testing
phases of the availability.
A facilities management team also was established, primarily to ensure:
(a) that PSNSY material stowage/laydown areas and facilities would be
ready to support the needs of the multifaceted EOH; and (b) that movement
of materials via rubber-tired or rail vehicles would accommodate the size
and weight requirements of some of the larger equipment items associated
with the backfit--e.g., active inert missiles, launch-tube liners, and
ballast cans. Working with NAVSEA, SSP, and Electric Boat, the project
management team made the arrangements needed to have D5 facilities-support
equipment delivered to PSNSY. Air Force C5A transport flights, manned
by Air Force reservists, were organized to air-freight the equipment from
various points of origin and then transfer it to tractor-trailers for
delivery to Puget Sound, where it was inspected, assembled, and made ready
for operation.
Innovating for Success
The project management team formed a process improvement team to undertake
the challenge of reviewing all of the submarine work processes used. The
team's goal was to streamline and/or redefine those processes that could
be updated to support the work necessary to complete the Alaska EOH on
time, within budget, and with no sacrifices in quality. One of the team's
major focus areas was the movement of the extraordinary amounts of material
associated with the D5 backfits. Eventually, the team approved a total
of 14 process improvements.
PSNSY undertook the design, manufacture, and certification of jib/box
style cranes to be placed over the forward and mid-ships Logistic Escape
Trunk (LET) accesses. The use of jib/box cranes allowed loads of up to
10,000 lbs. to be moved from the lowest levels of the ship to topside
areas without the use of portal type cranes. The loads then could be placed
directly on mobile carts that were part of a virtual material highway
system that extended to the edge of the drydock. A load then could easily
be rolled down to the drydock edge, where it was picked up by forklift,
put on a truck or other vehicle, and moved to any other site in the PSNSY.
This process significantly reduced the number of portal crane lifts required.
A temporary portable monorail system also was designed, and installed
in the lower level of the missile compartment to provide ease of movement
of equipment from the compartment to the area under the LET, where it
could be removed by the jib crane and highway system.
A trailer-mounted D5 ballast-can transportation fixture design also was
approved and certified, to allow "over the highway" transportation
of ballast-cans on public highways. (The only previously certified mode
of public transportation that had been approved was via rail car.)
Electric Boat developed an interpack-controlled hydraulic jacking fixture
to support the removal of launch-tube liners. This fixture was strong
enough to apply the breakaway force that might be required to remove an
installed C4 liner from its launch-tube assembly.
The Remaining Backfits
All of the innovations developed and the planning and execution strategies
undertaken for the first of the D5 backfits were approved with the needs
of the three remaining backfits taken into consideration. A major consideration
in the development of the planning and execution strategies, for example,
took into account that the SSBN USS Nevada's EOH, planned for FY 2001,
would start only nine months after the start of the Alaska's EOH. The
lessons learned during Alaska's EOH, therefore, would contribute in various
ways to the success of the Nevada EOH.
In January 1999 another project superintendent was assigned to the Nevada
EOH. This allowed the concurrent development and review of the planning
and execution products for both EOHs and ensured the incorporation in
the second EOH of the lessons learned from Alaska's EOH. Once this was
accomplished the planning and execution products were rolled over for
use by the Nevada project management team. This immediately contributed
to major "up front" cost savings in the Nevada EOH and allowed
the Nevada project team to assist in the "innovating for success"
strategies associated with the entire Trident II D5 backfit program.
The Alaska's EOH was completed seven days ahead of schedule (18 months,
three weeks). The Nevada EOH is on track to complete approximately two
months early (17 months), and 36,000 mandays under budget. The Ohio-class
SSBNs USS Henry M. Jackson and USS Alabama are currently scheduled for
backfits during their refueling overhauls in fiscal years 2005 and 2006,
respectively.
Use of COTS equipment reduced the size of the D5 navigation suite significantly,
allowing for a complete reconfiguration of the ship's navigation center
and the development of a new Analysis and Miscellaneous Equipment room.
COTS equipment also was used, but to a lesser degree, for some of the
command-and-control system modernization alterations, principally the
installation of a new-generation radar suite. The use of COTS equipment
greatly reduces the requirements previously imposed on existing support
systems, such as ventilation, cooling water, and electric power supplies.
Many of the other process and equipment improvements developed for the
D5 backfits--e.g., the jib cranes, material highways, and launch-tube
liner jacking fixtures--will be used during the conversion of the four
oldest Trident SSBNs to the SSGN configuration. Two of the conversions
will be carried out at Puget Sound, and the other two at the Norfolk (Va.)
Naval Shipyard. The ballast-can over-the-highway transportation fixtures
will be used by the Strategic Weapons Support Facilities of the Pacific
and Atlantic Fleets. Significant decreases in the time taken up by ballast-can
movements will be attained by use of these fixtures.
In short, the process improvements and lessons learned during the Alaska
and Nevada backfits will benefit the Navy far into the future. And the
members of the PSNSY project management team will continue to hone their
skills and work toward further improvements when they perform future Trident
work. *
|